Test ID:3251, Q36

Postby sumitraised » Fri Nov 30, 2012 9:00 pm

The problem is about sequencing the jobs that minimize total elapsed time to complete the job.
Given answer: (D) B-C-D-E-A

But the correct sequence should have been,

B-D-C-E-A

Check it out guys.
SUMIT CHAMLING RAI